Operational capabilities of the Anticorruption General Direction (AGD)
Projet terminé
The project was aimed to strenghten the operational capabilites of the Anticorruption General Direction (AGD) of the Ministry of Administration and Interior (MAI) of the Government of Romania by modern equipment and training of investigative teams. The project was part of the thematic fund security in Romania. Further information about this fund can be found among the additional information on the very bottom of this page.
Pays/région | Thème | Période | Budget |
---|---|---|---|
Roumanie |
Accroître la sécurité publique
Lutte contre la corruption et le crime organisé
|
01.03.2012
- 31.08.2013 |
CHF 273’500
|
- Increase of cases transferred by AGD to prosecution by 17%
- The needed surveillance equipment supplied, installed and effectively used
- The needed IT&C equipment supplied, installed and effectively used
- Ensuring the technical support for carrying out diagnosis studies on corruption aspects
-
Type d'aide Contribution à l'élargissement
Numéro de projet 7F07909
Groupes cibles |
Staff of Ministry of Administration and Interior |
Activités | The objectives have been achieved by strengthening the technical capacity of investigative teams to perform efficient undercover investigations (see result 1), by securing the IT and Communication systems that need upgrading to ensure that field operations can take place safely (see result 2) and by equipping the crime analysis teams with minimum statistical package to perform statistical analyses included in their general studies and discover crime patterns and series (see result 3). |
Résultats |
Résultats obtenus:
|
Direction/office fédéral responsable |
DDC |
Crédit |
Contribution suisse à l'UE élargie |
Partenaire de projet |
Partenaire contractuel Secteur privé |
Budget | Phase en cours Budget de la Suisse CHF 273’500 Budget suisse déjà attribué CHF 0 |
Phases du projet |
Phase 22
01.10.2017
- 31.08.2019
(Completed)
Phase 21
01.03.2016
- 30.09.2018
(Completed)
Phase 20
01.03.2016
- 30.09.2019
(Completed)
Phase 19
02.05.2016
- 28.02.2019
(Completed)
Phase 18
01.09.2014
- 30.06.2017
(Completed)
Phase 17
14.11.2014
- 31.08.2018
(Completed)
Phase 16
01.02.2014
- 31.07.2015
(Completed)
Phase 15
01.09.2014
- 28.02.2019
(Completed)
Phase 14
01.03.2013
- 30.06.2018
(Completed)
Phase 13
01.03.2013
- 30.11.2015
(Completed)
Phase 12
01.11.2012
- 30.06.2018
(Completed)
Phase 11
01.04.2012
- 31.03.2013
(Completed)
Phase 10
01.04.2012
- 30.06.2017
(Completed)
Phase 9
01.04.2012
- 15.06.2014
(Completed)
Phase 8
01.03.2012
- 31.03.2018
(Completed)
Phase 7 01.03.2012 - 31.08.2013 (Completed) Phase 6 01.03.2012 - 15.11.2014 (Completed) Phase 5 01.03.2012 - 30.06.2018 (Completed) Phase 4 01.03.2012 - 30.09.2019 (Completed) Phase 3 01.03.2012 - 30.07.2015 (Completed) Phase 2 01.01.2012 - 31.12.2017 (Completed) |