Erwartete Resultate: Output 1.1.2 Seven NTS teams are recruited, trained and equipped. NTS is conducted
Output 1.3.4 Reporting and mapping is completed. Post-Clearance Impact Assessment (PCIA) is conducted on all settlements in which clearance is conducted
Output 2.1.2 Five EORE teams are recruited, trained and equipped. EORE sessions are conducted, including distribution of EORE material
Output 2.3.4 Beneficiary data is collected. EORE post session impact assessment is conducted
Output 3.1.3 Eight manual Clearance teams, one mechanical mine clearence team and two technical survey dogs (TSD) are recruited, trained and equipped
Output 3.4 BAC, manual and mechanical mine clearance and TSD activities are conducted
Output 3.5 Clearance and/or progress reports submitted
Resultate von früheren Phasen: A first intervention of FSD has been co-funded by PHRD (lead) and SDC, together with the Principality of Liechtenstein and a contribution from Swiss Solidarity, for a total of 2,8 mio CHF. Seven FSD teams were recruited, trained and are operational in Kharkiv area, where they carry out mine action activities: explosive ordnance risk education (EORE), non-technical survey (NTS), technical survey (TS), battle area clearance (BAC), demining. The results of this project (surface cleared, number of mines/UXOs cleared) are not yet known, since it is continuing until March 2024.The assets (vehicles, tools, equipment) purchased for the first project will be transferred to the new project.
|